Dover Heights Wastewater Works Enter Final Stage as Sydney Water Advances Upgrade

Dover Heights wastewater works have entered their final stage, with Sydney Water progressing plans for an underground pumping station at Eastern Reserve to redirect untreated coastal wastewater into the Bondi treatment network.



The Refresh Vaucluse and Diamond Bay project reached its second and final stage in November 2026, following site establishment activities that began in September. Abergeldie Complex Infrastructure is delivering the Diamond Bay component, which includes pipelines to connect the remaining coastal outfalls with Sydney Water’s wider wastewater system. Once the new infrastructure is operating, wastewater that currently flows untreated into the ocean will instead be transferred to the Bondi Water Resource Recovery Facility.

Dover Heights Wastewater Works At Eastern Reserve

The underground pumping station is planned for Eastern Reserve, at the eastern end of Eastern Avenue. The clifftop reserve forms part of the Federation Cliff Walk, with the new infrastructure intended to sit largely below ground. Gravity pipelines installed using trenchless drilling will connect the Diamond Bay and Eastern Reserve outfalls to the pumping station. A separate pressure pipeline is planned along Oceanview Avenue, where open-trench construction will link the station to the existing Bondi wastewater network via Old South Head Road.

Dover Heights wastewater works
Photo Credit: UEA

Sydney Water will also upgrade wastewater pipes along Old South Head Road between Hamilton Street and Northcote Street to accommodate the additional flows. The design for Eastern Reserve was refined following consultation with surrounding communities and stakeholders. Sydney Water has identified preserving public recreational space and reducing construction impacts as considerations in the revised layout.

Industry Veteran
Industry Veteran

Construction arrangements include noise mitigation, approved heavy vehicle routes and trenchless installation methods where suitable. Chemical rock excavation may also be used where appropriate to reduce disruption.

Remaining Coastal Outfalls To Be Diverted

The Diamond Bay works follow an earlier construction package at Parsley Bay, where Sydney Water has been developing another underground pumping station and connecting pipelines to divert wastewater from the Vaucluse outfall. The earlier infrastructure was nearing completion when the final stage was announced on 10 November 2026, with completion and commissioning expected towards the end of the year.

Under the completed network, wastewater from the three targeted coastal outfalls will be treated at the Bondi Water Resource Recovery Facility before discharge through the existing deepwater ocean outfall, approximately 2.2 kilometres offshore. The upgrade is intended to end untreated discharges from the affected coastal outfalls and improve water quality along the eastern coastline. Wastewater will continue to enter the ocean after treatment, rather than being discharged directly from the existing clifftop outfalls.



The State’s November announcement places expected completion of the final-stage works at mid-2028, with Sydney Water’s project timetable remaining indicative. Sydney Water can be contacted about the project on 1800 641 349 or at vauclusediamondbay@sydneywater.com.au.

Published 17-November-2026